Scenario:
Alex, the project manager of the BCMS implementation project at Company ZY, developed a process to identify the required resources for establishing the BCMS. He discovered that the company lacked a well-integrated communication and information system and also needed additional office space to accommodate new hires.
What resources did the company need?
What is an aspect to consider when managing records?
Which system is primarily focused on managing documented information throughout its life cycle, including creation, storage, retrieval, and versioning?
An organization is trying to establish maturity targets for its existing processes. It is concluded that while some processes are implemented case by case, there is no standardized method for executing them. What maturity level does this indicate?
What should be avoided in the business continuity policy?