A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year.
The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor.
You need to configure the appropriate replenishment method.
Which coverage dimension should you use?
A company implements Dynamics 365 Supply Chain Management.
Due to increased demand and limited space in the work cell area tor product LOOM, you must subcontract overflow work to another company. You have the following requirements:
* Locate a warehouse at the subcontractor building.
* Support picking and shipping activity tracking.
* Associate costs of transporting materials between the locations in the cost of the finished product.
You need to modify the production flow.
Which three actions should you perform? Each correct answer presents part of the solution.
NOTE Each correct selection is worth one point.
A manufacturing company uses master planning in Dynamics 365 Supply Chain Management.
The production planner increases the lead time of an item. On the next master planning output the planner receives a cancel action message on existing purchase orders. The message includes a suggested earlier date for the planned purchase orders.
The demand for the item has not changed since the original purchase order was placed. Dynamic negative days is not used.
You need to resolve the issue.
What should you do?
You are the lead product design manage at a Process manufacturing plant.
A formula that produces egg yolks as a by-product. This by-product is added back into inventory at standard cost and can be used in other production batches.
You need to select the by-product cost allocation.
Which cost allocation type should you use?
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?